Viaduct Bridge Project
This project involved the construction of a large viaduct bridge. It showcases modern infrastructure development with reinforced concrete pillars.



Technical Specifications
Project Overview
Viaduct Infrastructure Development
The project involved the comprehensive construction of a 4.4 km main line expressway, integrating advanced bridge and tunnel engineering. Completed over a 22-month period, the project achieved high standards in structural precision, aesthetic integration, and safety compliance. It successfully met all regional government and transportation department performance targets.
Technical Specifications
Bridge Infrastructure
Tunnel Infrastructure
- Main Line Route Length
- 4.4 km
Earthworks and Construction
Earth and Rock Excavation/Fill
| Task | Volume |
|---|---|
| Earth and Rock Excavation | 1,081,000 cubic meters |
| Fill Volume | 917,000 cubic meters |
| Culvert/Channel Volume | 41,000 cubic meters |
Project Timeline
Key Milestones
- Start Date: January 15, 2010
- Main Line Dual-Rate Completion: June 30, 2011
- Final Completion: End of 2011
- Construction Duration
- 22 months
Quality and Standards
- Awards and Achievements
- Double Hit Double ExcellenceFirst Prize WinnerIndustry Standard Compliant