Power Generation Unit Expansion Project
This project focuses on expanding a power generation unit. The expansion includes industrial buildings and a chimney stack, suggesting a large-scale power plant facility.



Technical Specifications
Project Overview
Power Generation Unit Expansion
This large-scale power engineering initiative involves the installation of a 2 x 300MW power generation unit, including the main unit installation and associated external outbuildings. The project demonstrates comprehensive industrial capability, covering everything from initial structural steel hoisting to full equipment integration. The facility successfully completed its rigorous 168-hour trial operation phase, confirming its readiness for full-scale production and operational deployment.
Technical Specifications
Unit Capacity
Project Timeline
Key Project Milestones
| Milestone | Date |
|---|---|
| Project Department Established | Early 2006 |
| Boiler Steel Hoisting | March 15, 2007 |
| 168-Hour Trial Operation Completion | November 7, 2008 |
Project Scope
Scope of Work
- 15# Unit Main Installation
- External Outbuildings Construction
- Equipment Installation Works